1.5 Million Pound Mill Extension Update!!!!
I have just finished another fab meeting with potential building contractors, this time discussing the schedule of works and when certain areas will open!….
If we receive the planning permission back as expected on the 15th January 2016, the works will then start on 1st February 2016 and will take just 7 month to complete…
To simplify things the areas will open in the following order over the 7 months!
1st. The new ladies only zone
2nd. The new sports performance centre
3rd. Both new male & Female changing rooms at the same time
4th. The extended fire & ice spa
5th The main event of the swimming pool!!!
And to confirm no existing areas will close down during the works!!!